hard hat

Construction Updates

Weekly Updates

Report April 5th - April 9th

The PHS Phase 3 project is still going well. The tile crew has the women’s restroom wall tile almost completed. They only lack the top few rows on the fixture wall to finish that room. They will be moving to the men’s side next week.

 Framing is started in the old computer labs to make them into classrooms. The drains are roughed in for the new laundry and toilet that will open into the classrooms we built in phase 2. Voy is drilling the wall for the drains to continue outside.
 
 In-wall brackets are being set for the floating counter in the new commons. Then that wall  can be finished. We are waiting on door jambs before the walls in the new computer rooms can be drywalled on both sides. 
 
 They are scheduled to pour back the concrete floors that had to be cut for electrical and plumbing rough-in and the pit that was raised in the old boiler room next week.

Report March 22nd - March 26th

Good progress continues at the High School Project. Framing is moving into the ceiling fur-downs in the new commons area. Crews will be going into the culinary kitchen area next week. Plumbing on the group restrooms is roughed in and they are working on the french drain at the bottom of the old mechanical pit and backfilling it in. Wallcovering started “one-siding” the walls so the plumbing inspection can still be done next week. So far we are in a good place

Report March 15th - March 19th

Great progress at PHS Phase 3 this week. Framing is progressing at a good rate. Crews are past the group restrooms and working on the lounge area. Plumbers are close to  ready for an inspection on the restroom

Rough-in then drywall can start. Inspection should be the first part of next week. Electricians are roughing in boxes in the framed areas. Voy’s laborers saw cut the footing channel in the front part of the new media center this week also. So far this project is exceeding my expectations; I hope the progress continues at this pace!

Jim

Report March 3rd - March 12th

The Middle School Shelter Project is near completion. The gym floor received its final sanding and finish coat yesterday. Test and balance people are working on the HVAC air output. Not much left to do.

Phase 3 at the High School Project is progressing nicely. Voy has brought better subcontractors this time. Framing is moving at a very good pace. Plumbers are working to top out the group restrooms, and the electricians are roughing in their boxes and conduit as soon as the framing crew is out of an area. Crews will be working on some of the existing spaces over spring break to get further ahead before summer.

Report March 1st - March 5th

The Baseball/Softball campus passed the fire marshall’s final inspection. It is 100% occupiable now.

 
 The  PHS Phase 3 Project passed the under floor plumbing inspection and the floor has been poured back in the group bathrooms and the old freezer pad. Metal framing is scheduled to begin next week.

Report Feb. 22nd - Feb. 26th

Baseball/Softball and Middle School Shelter projects are both in the final stages. Punch list items are being addressed at both sites. We have the certificate of occupancy for the shelter and are working on scheduling the final inspection at the Baseball/Softball campus next week.

Phase 3 at Pryor High School got started this week. Saw cutting for the plumbing is underway, and the group restrooms have been roughed in. Waiting on a plumbing inspection on Monday; crews will then start pouring the floor back and framing can begin.

Baseball/Softball and Middle School Shelter projects are both in the final stages. Punch list items are being addressed at both sites. We have the certificate of occupancy for the shelter and are working on scheduling the final inspection at the Baseball/Softball campus next week.

Phase 3 at Pryor High School got started this week. Saw cutting for the plumbing is underway, and the group restrooms have been roughed in. Waiting on a plumbing inspection on Monday; crews will then start pouring the floor back and framing can begin.

Report Feb. 1st - Feb. 5th

The Baseball/Softball Project is winding down. We will do the punch walk with the Stacy Group on Tuesday. Turf is finished on the softball field. All the spoils are hauled off, and we have the bag of rubber infill material in storage to maintain the fields. Speakers have been installed along the front of the bleachers on both fields; roof decking is nearing completion, and final cleaning starts this weekend.

 
 The Middle School Shelter is in about the same place. Final cleaning and punch list items are being done. We are scheduled for the final gym floor coating beginning March 11.